August 29, 2011 Land Use Planning Attending: Steve Lenz, Marvin Massey, Paul Anderson, and City Public Works Director Larry Schommer Absent: Steve Reimer Work session began at 4:30 pm and the applications were reviewed Meeting called to order by Chairman Marvin Massey @ 5:02 pm. Minutes of the previous meeting were approved as presented. UNFINISHED BUSINESS Sheryl Klocker was not in attendance and LUP moved on to NEW BUSINESS NEW BUSINESS C. Turra Park Project Ted Rosencranz. Mr. Rosencranz presented a building application for construction of two duplexes to be located on lots 1&2 in the subdivision known as Turra Park. As current owner of Tuna Park, Paul Anderson had a conflict of interest, so he recused himself from LUP and went to the audience for the discussion. After review of the penuit and project plans, the following points were made: 1) LUP explained to Mr. Anderson & Mr. Rosencranz that City ordinances state duplexes are considered single family units and each unit constructed would be required to have individual water/sewer taps. 2) Mayor Paul Brooks was in the audience and he indicated that the City would contribute approximately $12,000 and the manpower to extend the sewer line across/under Edna street and to the edge of the property. 3) LUP also explained that each dwelling would have a front street assigned to it and the ordinance requiring a 25' setback would apply. And since proposed duplex unit#2 front-faced the alley, a 25' setback would be required from the alley easement. Since there was no quorum, LUP could not legally give approval/denial of the building permit or give a formal recommendation to the City Council. LUP requests that the City Council give a decision so Mr. Rosencranz will know what direction to proceed. UNFINISHED BUSINESS A. Sheryl Klocker joined the meeting late so LUP reopened UNFINISHED BUSINESS to review the Klocker Subdivision. Ms. Klocker gave a newly revised preliminary plat to LUP for review. LUP discussed the new plat and explained to Ms. Klocker the following points. 1) Historically the City has required developers to have all subdivision infrastructure completed prior to selling any lots. Infrastructure is defined as utilities including but not limited to water, sewer lines, and electrical, curb, gutter and paving. - — 2) Phasing of subdivisions has been permitted in the past, with each phase clearly outlined in a legal document. All infrastructure must be completed for each phase prior to the sale of any lots in each phase. Ms. Klocker agreed with the LUP points that were presented. She indicated that she would not be phasing her subdivision development. She also said she would be requesting a variance from the City Council regarding the infrastructure requirements and would be seeking approval from the City Council to sell a majority of the lots, then proceed with the curb, gutter, and paving requirements. Paul Anderson moved to approve the preliminary plat under the condition that all City of Sundance ordinances regarding subdivisions were completed prior to the sale of lots and in accordance with the rules regulating infrastructure requirements including curb, gutter and paving. Steve Lenz seconded, All in favor, motion passed. NEW BUSINESS LUP reopened NEW BUSINESS and the following permits were acted upon. A) Gary & Sandra Cronin—storage shed @ 1002 E. Sewell St. City Public Works Director, Larry Schommer, indicated the he and LUP member Steve Lenz had given prior approval to the storage shed permit. LUP accepted the recommendation as given as the permit was signed and the shed in place. B) Crook County Courthouse—relocate 12X16 storage shed, replace concrete & set an 8X8 air cooled chiller @309 Cleveland. Paul moved to approve, Steve seconded, All in favor, motion passed. C) Larry & Barbara Byrne—remove pond, expand parking and build 24X24 patio. Paul moved to approve, Steve seconded, All in favor, motion passed. OTHER Mayor Paul Brooks asked for the floor and gave a speech to LUP. The subject was to improve the working relationship between LUP and the City Council. He requested LUP to give decision (whenever possible) on permits and the Mayor and Council would do their best to support LUP's position. After Mayor Brooks relinquished the floor, 1) LUP asked the pei initees in the audience if they wanted to reopen the discussion on their pelinits. Mr. Rosencranz indicated he would like a decision from LUP, but since there was no quorum, LUP could not vote on his pelinit. 2) Ms. Klocker was asked if she would like LUP to reopen discussion and if she would like to submit a variance request to LUP. Ms. Klocker declined stating she would ask the Council for a variance and that she wasn't presenting a variance request to LUP at this time. Meeting was adjourned at 6:29 p Ami , N., AMP Minutes prepared b Atarr on August 31, 2011. 46r Or 011.