    		Attending: Steve Lenz, Marvin Massey, Paul Anderson, and City Public Works

    		Director Larry Schommer

    		Absent: Steve Reimer

     		Work session began at 4:30 pm and the applications were reviewed

    		Meeting called to order by Chairman Marvin Massey @ 5:02 pm.

    		Minutes of the previous meeting were approved as presented.

    		UNFINISHED BUSINESS

     		Sheryl Klocker was not in attendance and LUP moved on to NEW BUSINESS

    		NEW BUSINESS

     		C. Turra Park Project    Ted Rosencranz.  Mr. Rosencranz presented a building

     		application for construction of two duplexes to be located on lots 1&2 in the

     		subdivision known as Turra Park.  As current owner of Tuna Park, Paul Anderson

    		had a conflict of interest, so he recused himself from LUP and went to the audience

     		for the discussion.  After review of the penuit and project plans, the following

     		points were made:

       			1) LUP explained to Mr. Anderson & Mr. Rosencranz that City ordinances

    				state duplexes are considered single family units and each unit

    				constructed would be required to have individual water/sewer taps.

       			2) Mayor Paul Brooks was in the audience and he indicated that the City

    				would contribute approximately $12,000 and the manpower to extend the

    				sewer line across/under Edna street and to the edge of the property.

       			3) LUP also explained that each dwelling would have a front street assigned

    				to it and the ordinance requiring a 25' setback would apply.  And since

    				proposed duplex unit#2 front-faced the alley, a 25' setback would be

    				required from the alley easement.

     		Since there was no quorum, LUP could not legally give approval/denial of the

     		building permit or give a formal recommendation to the City Council.  LUP

     		requests that the City Council give a decision so Mr. Rosencranz will know what

     		direction to proceed.

     		UNFINISHED BUSINESS

     		A. Sheryl Klocker joined the meeting late so LUP reopened UNFINISHED

  			BUSINESS to review the Klocker Subdivision.  Ms. Klocker gave a newly

  			revised preliminary plat to LUP for review.  LUP discussed the new plat and

  			explained to Ms. Klocker the following points.

  			1) Historically the City has required developers to have all subdivision

       			infrastructure completed prior to selling any lots.  Infrastructure is defined as

       			utilities including but not limited to water, sewer lines, and electrical, curb,

       			gutter and paving.

     	-       2)  Phasing of subdivisions has been permitted in the past, with each phase

       			clearly outlined in a legal document.  All infrastructure must be completed

       			for each phase prior to the sale of any lots in each phase.

     		Ms. Klocker agreed with the LUP points that were presented.  She indicated that

     		she would not be phasing her subdivision development.  She also said she would

     		be requesting a variance from the City Council regarding the infrastructure

     		requirements and would be seeking approval from the City Council to sell a

     		majority of the lots, then proceed with the curb, gutter, and paving requirements.

       			Paul Anderson moved to approve the preliminary plat under the condition

     		that all City of Sundance ordinances regarding subdivisions were completed prior

     		to the sale of lots and in accordance with the rules regulating infrastructure

     		requirements including curb, gutter and paving.  Steve Lenz seconded, All in favor,

     		motion passed.

     		NEW BUSINESS

    		LUP reopened NEW BUSINESS and the following permits were acted upon.

     		A) Gary & Sandra Cronin storage shed @ 1002 E. Sewell St.  City Public Works

  			Director, Larry Schommer, indicated the he and LUP member Steve Lenz had

  			given prior approval to the storage shed permit.  LUP accepted the

  			recommendation as given as the permit was signed and the shed in place.

    		B) Crook County Courthouse relocate 12X16 storage shed, replace concrete &

  			set an 8X8 air cooled chiller @309 Cleveland.  Paul moved to approve, Steve

  			seconded, All in favor, motion passed.

     		C) Larry & Barbara Byrne remove pond, expand parking and build 24X24 patio.

  			Paul moved to approve, Steve seconded, All in favor, motion passed.

     		OTHER

    		Mayor Paul Brooks asked for the floor and gave a speech to LUP.  The subject was

    		to improve the working relationship between LUP and the City Council.  He

    		requested LUP to give decision (whenever possible) on permits and the Mayor and

     		Council would do their best to support LUP's position.

    		After Mayor Brooks relinquished the floor,

       			1) LUP asked the pei initees in the audience if they wanted to reopen the

    				discussion on their pelinits.  Mr. Rosencranz indicated he would like a

    				decision from LUP, but since there was no quorum, LUP could not vote

    				on his pelinit.

       			2) Ms. Klocker was asked if she would like LUP to reopen discussion and if

    				she would like to submit a variance request to LUP.  Ms. Klocker

    				declined stating she would ask the Council for a variance and that she

    				wasn't presenting a variance request to LUP at this time.

    		Meeting was adjourned at 6:29 p  Ami   ,

      							N.,	AMP

    		Minutes prepared b     Atarr   	on August 31, 2011.

   						46r

   							Or 011.

 

Wyoming State Archives 2301 Central Ave, Cheyenne, WY 82002 | (307) 777-7826

Wyo.Gov | Citizen | Business | Government | Visitor | Privacy Policy | Contact Us